U.S. Air Force keeps KC-46A in testing as key defects remain unresolved

Key Points
  • The U.S. Air Force has not completed KC-46A initial operational testing because final upgrades to the Remote Vision System 2.0 and boom telescope actuator redesign are still pending.
  • DOT&E said the tanker’s operational availability and mission capable rates remained below threshold requirements in fiscal year 2025 despite the fleet already being used for deployable missions.

The United States Air Force has still not completed initial operational test and evaluation for the KC-46A Pegasus tanker, with the program’s test cycle stretching on from 2019 as key technical fixes remain unfinished, according to the Pentagon’s Director, Operational Test and Evaluation annual report.

The report states that DOT&E approved the KC-46A IOT&E test plan in April 2019 and later told the Air Force in a May 2020 memorandum that it would not submit an IOT&E report until operational testing of a production-representative Remote Vision System was complete.

The continued delay matters because the KC-46A is already being used as a deployable tanker, but the Air Force still has not closed the full operational test cycle needed to confirm that the aircraft meets all required performance standards. The unresolved issues center on the Remote Vision System, or RVS, and the Boom Telescope Actuator Redesign, or BTAR, both of which remain tied to the completion of IOT&E.

- ADVERTISEMENT - CONTINUE READING BELOW -

According to the annual report, the Air Force continues to work with Boeing on technical upgrades to the KC-46A’s RVS and BTAR in order to meet operational requirements. DOT&E states that, once those upgrades are complete, IOT&E will resume. In fiscal year 2025, the Air Force Operational Test and Evaluation Center completed the cybersecurity portion of IOT&E, but the broader operational evaluation remains unfinished.

The report makes clear that the testing program is far along but still incomplete. AFOTEC has collected 85 percent of the planned IOT&E flight test data, yet it “cannot complete the remaining IOT&E events until the program office implements final RVS and BTAR upgrades,” DOT&E wrote. The report adds that operational testing of those upgrades will be integrated with developmental flight testing as much as possible, and that all remaining IOT&E events will be carried out alongside developmental test objectives.

That timeline leaves the KC-46A in an unusual position. The tanker is not a paper program or an early prototype. It is already fielded and approved by Air Mobility Command as a deployable asset to support U.S. Transportation Command taskings, although the report says that approval comes “with limitations.” In other words, the aircraft is operating in service while the formal test process needed for a full operational judgment is still open.

As described by DOT&E, the KC-46A is intended to replace part of the aging U.S. tanker fleet. The report says the Pegasus is an Acquisition Category IC program and the first increment of 183 replacement tankers for a fleet of more than 400 KC-135 and KC-10 aircraft. The aircraft itself is a modified Boeing 767-200ER commercial airframe adapted with military systems and refueling equipment for missions that include aerial refueling, airlift, aeromedical evacuation, emergency aerial refueling, air sampling, and support for combat search and rescue.

The RVS and boom system are central to the aircraft’s core mission. The Remote Vision System allows operators to conduct refueling operations using cameras and displays rather than direct visual observation from a traditional boom station. The boom telescope actuator is part of the mechanism used to control the refueling boom during contact with receiver aircraft. Problems in either area affect the tanker’s ability to perform aerial refueling safely and consistently across the range of operational conditions the Air Force expects.

DOT&E’s latest report shows that the Pegasus still falls short in other areas as well. The office wrote that the KC-46A “has not been able to meet several suitability metrics in past years, and this trend has continued through FY25.” It added that operational availability and mission capable rates remain “well below their threshold requirements.” Those are not minor bookkeeping measures. Availability and mission capable rates are core indicators of whether a fleet can generate aircraft consistently enough to support real-world operations.

The report also states that the program office continues efforts to remediate previously reported Category 1 deficiencies, including the RVS and BTAR improvements and other airframe deficiencies identified during earlier testing. On effectiveness, DOT&E said the KC-46A is capable of refueling 26 of 27 candidate receiver aircraft types, though some restrictions remain that limit availability in certain environmental conditions and aircraft configurations. Testing of the 27th receiver type is expected to resume after the BTAR upgrade is complete.

Aerial refueling is one of the Air Force’s core enabling missions, supporting long-range strike, fighter deployments, bomber operations, mobility flights, and joint operations across wide theaters. Delays in fully closing operational testing for a tanker fleet replacement program therefore carry weight beyond a single aircraft type. A tanker that remains under operational limitations or below availability thresholds affects how reliably the force can generate support for other combat aircraft.

Readers who wish to follow our weekly coverage can subscribe to the Weekly Defense Roundup.

If you wish to report a grammatical or factual error in this article, please let us know by using the online form.

Executive Editor

Support The Defence Blog

Independent reporting takes resources. Join us on Patreon.

Become a patron

More Like This

US Navy orders 50 prototypes of its cheap new hypersonic weapon

Hypersonic weapons have long been the most expensive category of precision strike munitions in any military's arsenal, costing tens of millions of dollars per...

US invests $400M at Morón base despite Spain’s combat operations ban

The United States Air Force has awarded $400 million in construction contracts to seven Spanish companies to maintain and improve Morón Air Base, a...

US Marines’ most powerful helicopter gets a $525M upgrade program

The U.S. Marine Corps operates the most powerful helicopter in the American military inventory, a machine capable of lifting 16,329 kg (36,000 lb) of...

Pentagon awards $2.3B F-35 sustainment contract to Lockheed Martin

The U.S. Navy has awarded Lockheed Martin a $2.3 billion contract to establish and sustain new operating sites for the F-35 Lightning II, the...

Gallatin AI wins US Army contract for contested logistics software

Feeding, fueling, and arming a corps-sized force of tens of thousands of soldiers across months of sustained combat, with supply lines potentially stretching a...